Turnstiles and speed gates

Turnstile installation: what to prepare in the floor, power and network

Reviewed on · Written by the technical team at Control de Acceso Valencia

Quick answer

A turnstile needs a firm, level floor to fix to, a conduit to its base for power and data, a protected electrical circuit, a network point for the controller and enough space before and after the lane. Planning all this before the floor is laid avoids opening up a finished floor.

1. The floor

  • Firm and level. Turnstiles are anchored to the slab or screed. On a floating or raised floor a base or reinforcement is needed.
  • What lies beneath. Underfloor heating, pipes, conduits or a waterproof membrane limit where you can drill. Ask for drawings first.
  • Expansion joints. A cabinet must not straddle a joint.
  • Outdoors. A concrete base with a fall to shed water.

2. Conduits

Power and signal cables (data, readers, alarm signal) must reach each base in separate conduits. A speed gate also needs a link conduit under the lane between its two cabinets.

  • New build or refurbishment: conduits embedded before the floor is laid.
  • Finished floor: chase and reinstate, floor trunking or raised floor.

3. Power

  • A circuit from the board with its own breaker and RCD protection.
  • Voltage and load as per the manufacturer's data sheet.
  • Earth connection.
  • Backup power if they must work in an outage. Decide first what they should do without power: go free or stay locked (evacuation).

4. Network and control

  • A network point for the controller or the turnstile itself, depending on the system.
  • A protected location for the controller and power supply.
  • A cable to the fire panel for the release signal.
  • A cable to reception if there is a manual release button.

5. Space

  • Total width: turnstiles, cabinets and the accessible gate added together (how many you need).
  • Clear depth before and after, so queues do not form in a doorway or on stairs.
  • Side closure (railing or glass) so the line cannot be bypassed.
  • A step-free accessible route (accessibility).
  • Access to open the cabinets for maintenance.

Who does what

TaskUsually done by
Conduits and floor reinstatementBuilding contractor
Electrical circuit to the pointAuthorised electrician
Network pointTelecoms installer or IT
Fixing, wiring and commissioningTurnstile installer
Fire panel signalFire protection maintainer

The quote should state explicitly which items are included and which are not (how to compare quotes).

Common mistakes

  • Laying the floor before deciding where the turnstiles go.
  • One conduit for both power and data.
  • Forgetting the cable to the fire panel.
  • Cabinets so close to the wall that they cannot be opened.

For a site visit and a pre-installation drawing, this is our turnstile installation service.

Frequently asked questions

How long does it take to install a turnstile?

With pre-installation done, fixing and commissioning are usually quick; what stretches the schedule is conduit work and coordination with other trades. It depends on the case.

Can it be installed on a raised floor?

Yes, but the turnstile is not fixed to the tiles: it needs a frame or base that transfers loads to the slab.

This guide is for information only and is not a substitute for legal advice or for the technical design of each installation. Regulations change: always check the current text at the official source.